The roof sheeting is now fully complete, marking a key milestone in achieving a watertight structure. On Level 7, wall and ceiling framing is nearing completion and first fix of services have commenced. Meanwhile, Level 6 has seen wall and ceiling framing completed, plasterboard installed, and the first coat of paint is now underway.